Approved-online-essay-writers

How do Earned Value SPI (based on $) and Earned Schedule SPI differ?

Using the date for Problem 14, add the resource assignments to each of the activities and input their hourly rates as shown. Construct an earned value chart for the project. Which activities have negative variances? What is the estimate at completion (EAC) for the project? (Hint: Remember to click “Set baseline” prior to creating EVM table. The EVM table is found by clicking on the “View” tab, then “Tables,” then “Other Tables”.) Problem 14 (Optional—Based on Earned Schedule discussion in Appendix 13.1.) Suppose you have a project with a Budget at Completion (BAC) of $250,000 and a projected length of 10 months. After tracking the project for six months, you have collected the information in the table below. a. Complete the table. How do Earned Value SPI (based on $) and Earned Schedule SPI differ? b. Calculate the schedule variances for the project for both Earned Value and Earned Schedule. How do the values differ? Schedule discussion earned Schedule* Research and practice using Earned Value Management (EVM) has shown that this method for project tracking and forecasting is reliable and offers the project team an accurate snapshot of both the project’s current status and a forecast of its completion conditions. However, in recent years, some critics have noted that EVM also has some important limitations. One of the most important of these limitations is the fact that all project status information is derived in terms of the project’s budget, including the project Schedule Performance Index (SPI) and schedule variance. A second concern voiced about EVM is that it becomes less precise (unreliable) the farther a project progresses and that by the latter stages of the project, the information derived from EVM may be either unjustifiably positive or negative. Finally, it has been suggested that EVM becomes an imprecise metric for projects that have already overrun, that is, whose duration has exceeded the original baseline end date. In other words, how do we determine the ongoing status of a project once it is officially “late”? Let us consider these objections to EVM in turn. First, we know that EVM is derived from the project’s budget, not its schedule performance, but intuitively, it makes better sense that a project’s schedule performance should be in terms of units of time. For example, remember that Schedule Variance (SV) is calculated by Earned Value (EV) minus Planned Value (PV), and the formula for finding the Schedule Performance Index (SPI) is SPI = EV/PV. Thus, we are assessing the project’s schedule performance, not as a function of time, but of money. We can see this graphically by considering Figure 13.19, which shows a generic project EVM measure. The vertical axis of the performance chart is in terms of budget dollars, and the resulting schedule variance is also expressed in terms of the project’s budget. The EVM metrics for schedule, then, are Earned Value (EV) and Planned Valued (PV). The second concern suggests that the closer to completion a project gets, the less precise and useful is the information that EVM provides. The significance of cost-based ratios used with planned duration to predict a project’s final duration can be illustrated by a simple example. Assume a project with a budget of $1,000 has completed most of its planned work, with EV = $990, PV = $1,000, BAC = $1,000, and PD (Planned Duration) = 12 weeks. These metrics give an SPI of 0.99, which yields a final duration of 12.12 weeks: Estimate at Completion = 1/.99 * 12. We can see from simple inspection that as EV approaches PV, and ultimately BAC, forecasted project duration decreases, because the upper limit for EV is always BAC. Regardless of whether this calculation is performed during week 10 or week 15, the cost-based ratio yields the same results and can show that an in-progress project has a forecasted completion date in the past. This issue suggests that EVM becomes less precise the closer a project is to its completion. Where early indicators are reasonably accurate, by the final stages of the project’s life cycle, the project schedule metric (remember, it is based on monetary units) is likely to show encouraging evidence of completion. However, it is during the final stages of the project that Cost Variance and Schedule Variance data begin to diverge. Critics of EVM have pointed out this quirk in the system; as a project moves closer to its supposed completion date, its planned value converges on the project’s planned cost—that is, PV = BAC (Budgeted at Completion). However, with late projects, the project’s planned value has usually already converged on the project’s overall budget (i.e., PV = BAC), while EV is still incrementally achieving this value. Once PV = BAC at the project’s planned completion date, the project cannot be measured as being “later.” In effect, there are measurement errors that do not become apparent until a project is already late. The solution that researchers have adopted is to introduce the concept of earned schedule (es) project management. Earned Schedule recognizes, first, that for accurate forecasts of project schedule, some unit of time must be the metric to consider, rather than EVM’s cost-based approach. Earned Schedule uses a relatively simple formulation to achieve its purpose, which is to derive a time-based measurement of schedule performance by comparing a project’s EV today (actual time) to a point on the performance measurement baseline (the Planned Value curve) where it should have been earned. The difference in the two times represents a true time-based Schedule Variance, or, in Earned Schedule notation, SVt. The derivation of Earned Schedule metrics is shown in Figure 13.20. As the figure demonstrates, the Schedule Performance Index for any project can be reconfigured from the original, SPI($) = EV/PV, to the alternative: SPI(t) = ES/AT. In the second equation, the Schedule Performance Index for an Earned Schedule calculation divides the Earned Schedule value by Actual Time. Likewise, in this second configuration, Earned Schedule variance equals Earned Schedule minus Actual Time (ES – AT). To calculate Earned Schedule, we use the project’s current earned value (EV) to identify in which time increment of PV the cost value occurs. The value of ES is then equal to the cumulative time to the beginning of that increment plus some portion of it. For example, suppose we wished, at the end of June, to calculate the ES of a project that began January 1 (see Figure 13.20). We use monthly increments in our calculation; thus, because we are at the end of June, AT = 6. We can see visually that by the end of June, the project’s schedule has slipped some degree; in fact, we see that we have completed all of April and some portion of May’s work by the end of June. We can use the following formula to determine the project’s ES: where C is the number of time increments on the project schedule baseline where EV Ú PV. In our specific example above, with monthly time increments, the formula becomes: We can see an example of a complete Earned Schedule calculation in the following case. Suppose we have been collecting data on the status of our project for the past six months, using the standard EVM method. Table 13.16 gives this information. Calculating the ES for January, we have the values: EV (Jan) = 95 PV (Jan) = 105 We can use this information to calculate ES, SV, and SPI for the project, using the formulas we found previously: Using this information, let’s complete the ES table to the end of June (see Table 13.15). The table now aligns with Figure 13.20. We can see from the information we have calculated in Table 13.17 coupled with Figure 13.20 that by the end of June, a comparison of the project’s PV with actual ES shows a serious slippage. Specifically, by the end of June, we have only completed the project’s schedule to approximately halfway through the May period. Furthermore, the schedule variance and SPI values have been worsening over the past four months, suggesting that the slippage is accelerating. This information is not necessarily obvious from the standard earned value table, which uses project budget dollars. Finally, research demonstrates that the SPI based on dollars versus the SPI using time can become very different as the project moves toward completion. Thus, as noted earlier, real data confirm one of the central concerns about EVM, namely, that its estimates for schedule become increasingly imprecise the later into the project we move. The relative accuracy of Earned Schedule versus EVM can be further illustrated when we use it to anticipate schedule variances and possible project delays. Let’s use the following example to compare the results we might find when using EVM versus Earned Schedule. Suppose we have a project planned for 18 months’ duration (PD) and a total budget of $231,280 (BAC). At the end of 16 months, $234,080 has been spent (AC) while we only have achieved an EV of $207,470. We first calculate budget performance, or Cost Variance (CV), as CV = EV – AC, or: Schedule Variance (SV), for our example, also can be calculated based on this information. Recall that SV = EV – PV, or: The above figures show that the project is over budget and behind schedule, but to what degree over the life of the project? We can also use this information to calculate Schedule Performance Index (SPI) and Cost Performance Index (CPI) for the project. Respectively, these values are found as: We know from earlier in this chapter that the simple interpretation of these values suggests that each dollar spent on the project is only producing 89 cents’ worth of work, and each 8-hour day is producing only 7.5 hours of effective work. What would the long-term effects of these values be on the project? One way to determine that is to estimate the final schedule duration, the Estimate at Completion for Time (EACt), found through the following formula: We can solve a similar equation to find the Estimate at Completion (EAC) for the project’s budget. Dividing the BAC of $231,280 by the CPI (0.89) yields an estimated cost at completion for the project of $259,870. To see how Earned Value and Earned Schedule calculations can lead to important divergence, let’s use the same information from the above example, shown in Table 13.18, with ES formulas to determine the project’s schedule status when we use time metrics, not budget data. Recall that at the end of month 16, we are interested in determining the status of the schedule. Our formula to calculate Earned Schedule (ES) is given as: Applying our Schedule Variance equation, SVt = ES – Actual Time (AT), we find that the project is 1.31 months behind schedule (SVt = 16 – 14.69). We can now apply this information to the Earned Schedule’s Schedule Performance Index (SPIt) formula, given as: Lastly, we can derive our projection for the project’s final duration, using the Independent Estimate at Completion for time (IEACt), and come up with the duration forecast, as shown: Consider the results condensed into Table 13.19. When we compare the variances, performance indexes, and projections to completion for the project using EVM versus Earned Schedule, we can see some important discrepancies. First, note the obvious point that for schedule variance, Earned Schedule provides an actual duration estimate based on time, not dollars. Thus, we can relate to the information more easily. However, it is more intriguing to see the differences when Earned Schedule is applied to the SPI in order to determine the likely overall project duration. In this case, the Earned Schedule value suggests final project duration of 19.51 months, or about half a month later than a similar calculation using EVM. Earned Schedule is a relatively new concept that has sparked debate within the project management community. To date, most research supporting Earned Schedule has come either from small samples in field tests or through computer models. Nevertheless, the underlying arguments supporting Earned Schedule do bear careful consideration. Research suggests that EVM has a tendency to become unreliable as a project moves to completion, and thus it is important to understand to what degree that is of the ES approach actually improves. Another advantage of Earned Schedule is that the calculations are relatively straightforward and the data can be manipulated from the same information obtained for EVM calculations. Thus, at a minimum, Earned Schedule offers an important “check” to verify the accuracy of EVM for project monitoring, particularly as the project begins to overrun its baseline or move toward completion.19

We Write Essays for Students

Tell us about your assignment and we will find the best writer for your paper

Get Help Now!

 

PLACE THIS ORDER OR A SIMILAR ORDER WITH LITE ESSAYS TODAY AND GET AN AMAZING DISCOUNT

The post How do Earned Value SPI (based on $) and Earned Schedule SPI differ? appeared first on Cheapest Academic Custom Papers.

Welcome to originalessaywriters.com, our friendly and experienced essay writers are available 24/7 to complete all your assignments. We offer high-quality academic essays written from scratch to guarantee top grades to all students. All our papers are 100% plagiarism-free and come with a plagiarism report, upon request

Tell Us “Write My Essay for Me” and Relax! You will get an original essay well before your submission deadline.

PLACE YOUR ORDER